Dock Leveller Refurbishment at Petikemas

25+ units repaired in two weeks at Port Klang Free Zone.

WhatsApp Us for a Quote

Project at a glance

SiteD’Buaya Warehouse, Port Klang Free Zone
ScopeMore than 25 dock levellers
DurationTwo weeks

Work completed

Hydraulic servicing

  • Addressed hydraulic leaks on site.
  • Carried out broader maintenance after finding dust buildup and power packs running hot.

Factory refurbishment

  • Removed units with cracked support-beam welds.
  • Dismantled, rewelded and reassembled the units at our factory.

Curb-angle reinforcement

  • Added reinforcing bars at damaged curb angles.
  • Used chequer plate to strengthen affected rear curb-angle areas.