Dock Leveller Refurbishment in Port Klang Free Zone
Methodcon refurbished 25 existing dock levellers in 2 weeks at a Port Klang Free Zone (PKFZ) warehouse. The team repaired hydraulic leaks, rebuilt units with cracked support welds and reinforced damaged dock pit edges.
WhatsApp Us for a Site AssessmentInside the PKFZ loading bays
A dock leveller is the steel platform built into the loading bay floor. It bridges the gap between the warehouse floor and the truck or container floor so forklifts can move goods across. These photos show the layout of the bays and where the leveller sits in the dock pit.
Deck damage and workshop refurbishment
Project at a glance
| Site | Warehouse in Port Klang Free Zone (PKFZ) |
|---|---|
| Scope | Refurbishment of 25 dock levellers |
| Duration | 2 weeks |
What we repaired across the loading bays
Hydraulic repairs on site
- Repaired hydraulic oil leaks on site.
- Serviced hydraulic power packs affected by dust build-up and overheating.
Workshop refurbishment
- Removed units with cracked support-beam welds.
- Dismantled the affected units, repaired the cracked welds and reassembled the units at our workshop.
Dock pit edge reinforcement
- Added reinforcing bars to damaged steel angles around the dock pit.
- Used chequer plate to reinforce damaged sections at the rear of the dock pit.
Planning refurbishment for an existing site?
If several bays have oil leaks, recurring breakdowns or visible deck and frame damage, start with a bay-by-bay inspection. Use the findings to decide which units need on-site repair, which need workshop refurbishment and which should be considered for replacement. Where bays are still in use, plan the work around your loading schedule.
Request a dock leveller site assessment
Send us your factory or warehouse location, the number of dock levellers, affected bay numbers and any fault photos. We can discuss the condition of the units and what to prioritise to support safer day-to-day use.